StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Just Say NO To Utility Representatives Sneaking Around Jefferson County

4/16/2025

1 Comment

 
We've had multiple reports recently that FirstEnergy (possibly masquerading as your local electric company, Potomac Edison) has been sneaking around Jefferson County, knocking on doors and trying to get landowners to sign permission forms allowing the utility to perform its "surveys" outside the existing easement, on the landowner's property instead.  It has also been reported that people are being approached by telephone.

One person even reported that the utility representative said the company would be seeking to expand its easement and he would be delivering an offer soon.

Just say NO!

You are not required to permit the company on your property... and that is why they need your permission to do it.  Don't give away your property rights like that!

What's a survey?  In addition to the normal metes and bounds survey you're probably thinking about, transmission developers also want to do environmental, historic, cultural, and geotechnical surveys.  The environmental surveys are looking for the presence of certain bats, or turtles, or other endangered species.  They are also looking for wetlands and other land features.  They are looking for historic resources.  They want to dig and perform archeological surveys.  And they want to bring large equipment on your property and drill core samples to see if it's possible to anchor a giant transmission tower foundation 30 feet down.  Sometimes, they need to cut trees and vegetation to get a line of sight (or so they've told the landowner).  If you want to open your property up to a parade of people using it for transmission development surveys, then go ahead and sign their form.  Otherwise, tell them to get lost and come back when they have a permit from the West Virginia Public Service Commission (WV PSC) in their hand.

FirstEnergy does NOT have a permit from the WV PSC at this time.  In fact, FirstEnergy has not yet even applied for a permit.  In order to apply for a permit, the company is required to undertake community engagement (dissemination of project information to the public such as meetings, routes and maps, newspaper articles, a website, informational mailers).  FirstEnergy hasn't even done that yet.  Instead, it wants to divide and conquer landowners, keep them isolated and uninformed, and get them to sign away their rights for pennies on the dollar.

Why is FirstEnergy so afraid of us?  Because last time they tried to build an unneeded transmission line here, they lost!  There's power in numbers and information sharing between neighbors.  There's power in grassroots community opposition, and we need to circle the wagons to keep our community safe.  Don't let FirstEnergy's representatives cut you from the herd and isolate you from your neighbors.  Tell them to stop calling and/or get off your property until they have a permit to build their transmission line from the WV PSC.

There's a rhythm to planning and building a new (or even re-built) transmission project.  The FIRST thing the utility usually does in your local community is schmooze your local elected officials and try to get them on their side.  That ship has sailed here in Jefferson -- we beat them to the County Commission and FirstEnergy has provided absolutely ZERO information to our local government. 

​The SECOND thing the utility usually does is to schedule what it calls "Open House" public information "meetings."  They really think one trip around this room is all it takes to turn you from transmission skeptic to transmission advocate!
Picture
FirstEnergy has not announced any public meetings yet.  In fact, there's no indication that it ever will happen at all. It seems FirstEnergy has skipped some steps because contacting landowners and asking for permission to survey typically comes AFTER these meetings, the publication of a website, news articles, and community notification through postcards or other mailers.

What kind of dirty deeds and misinformation is FirstEnergy spreading in our community that can't stand the sunlight of public scrutiny?

Over the years, I've assisted communities on so many transmission projects that I've come to know the "utility playbook" for ramming a new transmission project through a resistant community by heart.  However, it seems the utility has updated their playbook lately, and I'm gonna call it "Utility Playbook - Desperation Volume 2.0".  The new volume dispenses with public information and preys on landowners (that's right, I said PREYS) to get then to sign away their rights before they have necessary information to make a reasoned decision.

There's another community to our north in Pennsylvania that seems to be experiencing an identical transmission project information desert populated by the same shady characters approaching landowners and saying the most outrageous things, such as:
“People are trying to take approximately 5 acres of my property and giving me absolutely no information,”  she said. “They’ve called me, and they want to do a survey, but they won’t give me any information.”
Sound familiar?  Or, how about this?
“(PPL) was asking if (residents) would sign a document and if they didn’t sign the document, they couldn’t tell them about the project, I’m being told,” Walsh said. “Other people were being offered crazy low value for property.”
He said at least 10 people told him of instances like this....
Enticement to sign away your rights to get information?  That's plainly criminal.

FirstEnergy needs to pull its camel nose out from under the wall of Jefferson County's tent.  We're not stupid, and we're not for sale.  Creating an information desert is about the stupidest stunt they could perform.  They must have signed with Charles Ryan again to get such stellar advice!  I know how much FirstEnergy loves to read my blog, so here's a word to the wise.  GET BUSY WITH THE INFORMATION.  THE LONGER YOU WAIT, THE WORSE IT'S GOING TO BE.

And while we're waiting... let's hold our own informational meeting for the community!  Everyone is welcome to join us on April 29 at 7:00 p.m.!  FirstEnergy spies at the meeting will be separated from the herd and given last year's Halloween candy and bottled water from Jefferson County's underground pollution plume.  I can spot you guys a mile away.  Dork has a certain fashion sense that's impossible to hide.   See you there, everyone!
Picture
1 Comment

Washington Post Says The Quiet Part Outloud

4/20/2024

1 Comment

 
Picture
Our power appetite is bigger than our power supply.  The "renewable transition" isn't working.  We are losing large baseload power generators and not replacing them and we're adding too much load.  Our electric system is not sustainable.  It's a simple math equation.

Back in January I was contacted by a reporter from the Washington Post who had been writing about the proliferation of data centers in Northern Virginia and wanted to investigate how Virginia's out-of-control building was impacting people in surrounding states.  Virginia's data center problem is no longer just Virginia's problem.  It has now spread to the entire 14 state PJM Interconnection region.

​Here's his story that began back in January.

​
For us, the story began last summer when we found out about PJM's transmission plan for multiple new high-voltage transmission lines to import more power to data center alley.  We followed it through PJM's planning process and though we protested and asked for other solutions, PJM approved three new 500kV transmission lines and a whole bunch of smaller segments and substations.  During PJM's TEAC meetings, I remarked several times that the new transmission was feeding from existing legacy coal plants in West Virginia and was actually increasing emissions and in no way helping the "renewable transition."  Every time I mentioned it, PJM was quick to claim that the new electric supply would come from "all resources, including renewables."  PJM seemed rather sensitive about the reality of its plan and vehemently denied it.  Deny this article, PJM.  It's all there in living color.

Virginia has renewable energy laws that prohibit the building of new fossil fuel generation (gas, coal).  But yet Virginia is building an incredible amount of new data centers that use outrageous amounts of power that is simply not available on the current system.  Virginia's renewable energy plan is a virtue signaling lie.  Instead of building the electric generation it needs, Virginia intends to IMPORT electricity from surrounding states, even coal-fired power from West Virginia.  ESPECIALLY coal-fired power from West Virginia.  How is Virginia's "renewable energy" law cleaning up the environment?  It's not.  It's making the situation worse.

After Tony started working on this story for the Washington Post, FirstEnergy made an announcement that bolstered what I had been saying... PJM's transmission plan is increasing the production of coal-fired electricity in West Virginia.  FirstEnergy announced it was abandoning its goal to decrease its carbon emissions by 2030 by throttling back its Ft. Martin and Harrison coal-fired power plants near Morgantown.  FirstEnergy said it was necessary to abandon that goal because those resources were necessary to provide reliability in PJM.   In other words, FirstEnergy will throttle up its electricity production at those plants in order to provide supply to PJM's new transmission line that begins at the nearby 502 Junction substation and ends at No. Va.'s data center alley in Loudoun County.  Ft. Martin and Harrison directly connect to 502 Junction via dedicated 500kV transmission lines.  Also connecting directly to 502 Junction is the Longview coal-fired power plant in Morgantown and AEP's Mitchell coal-fired power plant in West Virginia's northern panhandle.  It's more than 5,000 MW of hot and dirty coal-fired electricity and if the line is constructed it's heading right for Northern Virginia, along with some smog and air pollution.  Data Centers are filthy!  And PJM is a filthy liar.

Along the way to No. Va., PJM's new coal-by-wire extension cord will expand existing transmission rights-of-way closer to homes, schools, parks and businesses.  Expanding existing easements makes it impossible for the utility to avoid sensitive things like they could if they were siting a new corridor.  Anyone living along the existing corridor, like the Gee family, is going to be steamrolled right over. 

The "using existing rights-of-way" propaganda is another huge PJM lie I brought up over and over during TEAC meetings.  It's a new easement all the way because it cannot be constructed within the existing corridor.

And guess what?  Along with new pollution and new land acquisition using eminent domain, West Virginians will PAY for this destruction/construction in higher electric bills, along with every other ratepayer in the PJM region.

And we get NOTHING for our trouble.  Virginia gets new tax revenue building things they can't power while crowing about how "clean" Virginia is, and the rest of us get the impacts and the bill.  We're NOT your sacrifice zone.

Washington Post reporter Tony Olivo did a fantastic job investigating and reporting on this story.  He spent a day with us here in Jefferson County and drove from one end of the county to the other meeting people, and Washington Post photographer Sal got lots of photos and drone footage along the way.  Then these two guys drove all the way out to 502 Junction and Morgantown to do the same there.  They spent an enormous amount of time on this story and it shows.

One of my favorite images in the story is the new solar "farm" near Charles Town taken from the drone.  It shows how the company building it scraped off all the vegetation and top soil and left nothing but bare earth and erosion that is killing the Shenandoah River.  Clean energy ain't so clean, is it?

And let's talk about that "clean energy", shall we?  Wind and solar cannot create the amount of electricity needed for new data centers, even if they cover Virginia with turbines and panels from end to end.  The data centers need a plentiful and reliable supply they can only get from fossil fuels.  A few solar panels on the roof of the data center won't do a thing to cure this problem.  It may only keep the lights on in the restroom... during the day.  Renewables cannot power our energy intensive society.  We're not replacing the generation we're shutting down in the name of carbon reduction, and there's no chance that we can ever catch up at this point.  Data centers are too big a drain and Virginia can't stop building them.

If you have any doubts, check out the Generation Fuel Mix pie chart on PJM's website at any time.  Renewables provide only a tiny slice of PJM's power supply and it will never change as long as we keep increasing power load with new data centers.

Bravo to Washington Post for exposing Virginia's dirty data center reality!

​And let's get to work, Jefferson County.  We've got a power line to stop!



1 Comment

FirstEnergy Lights Up Some Schadenfreude

2/13/2024

1 Comment

 
Dear FirstEnergy,

​Right now you are down and out and feeling really crappy....
And when I see how sad you are it sort of makes me.... 

HAPPY!
I have been singing this tune since I read about the latest indictments of former FirstEnergy executives Chatty Chuck Jones and Michael Dowling, along with their paid off regulator Sam Randazzo.

FirstEnergy criminals "on the loose". (Headline has since been changed to something less sensational, but it was fun while it lasted.)
Picture
Chatty Chuck and friends finally surrendered and got their mug shots taken.  I wonder if someone will create some fake $2 bills with their mug shots on them?  Maybe the wives can get together and find a way to continue their fortunate lifestyles without these guys? The $2 bills would be the perfect currency for bribing regulators in the future.
Picture
Chatty Chuck is no longer smiling.  I bet he's no longer chatty, either.  Why do I call him Chatty Chuck?  It's because of the absurd press he generated back in 2013 when doing a deal to plaster FirstEnergy's name on Cleveland Brown's stadium.  It was one of the biggest PR fails I have ever seen.  (The Browns ditched FirstEnergy after the scandals started).

Chatty Chuck (so named because of his arrogant confidences shared with the reporter) demonstrated his mastery of "the deal" by telling the reporter:
​Said Jones, “Let’s just say we figured out how to keep it under wraps.”
I guess he couldn't figure out how to keep his bribery of the Chairman of the Public Utility Commission of Ohio under wraps.  This is an even more epic fail for Chatty Chuck.

Even more, this is a good look at all the things that go on behind the scenes between regulators and regulated.  Think FirstEnergy is the only utility doing it, or that Ohio is the only place utilities do it?  I'm thinking no.

I guess I'll play that tune again... "CEOs in shackles."  Yes, indeed!  That makes me happy.  Karma is a bitch, Chuck!
1 Comment

Dirty No.Va. Data Centers Cause Failure to Reach Climate Goals

2/12/2024

0 Comments

 
Regional utility FirstEnergy announced on Friday that it was abandoning its  interim 2030 climate goal.
After careful consideration and evaluation, in late 2023 we made the decision to remove our interim target to achieve a 30% reduction in GHG emissions by 2030 from a 2019 baseline since achieving it is not entirely within our control. 
And why is that, exactly?  Well, here's as close to the truth as FirstEnergy wants to get:
Achieving the 2030 interim goal was predicated on meaningful emissions reductions at our Fort Martin and Harrison power plants in West Virginia, which account for approximately 99% of our greenhouse gas emissions.
We've identified several challenges to our ability to meet that interim goal, including resource adequacy concerns in the PJM region and state energy policy initiatives. Given these challenges, we have decided to remove our 2030 interim goal. Through regulatory filings in West Virginia, we have forecast the end of the useful life of Fort Martin in 2035 and for Harrison in 2040.
The climate goal has been eliminated because FirstEnergy cannot reduce emissions at its Fort Martin and Harrison coal-fired power plants in West Virginia.  And why did FirstEnergy think it could reduce emissions in 2020, only to backpedal less than 4 years later and abandon its interim goal?  What changed in late 2023?  What are the PJM "resource adequacy" and "state energy policy initiatives" that made FirstEnergy abandon its 2030 goal?

​This!
Picture
PJM's new transmission project designed to help import 7,500 MW of energy to Loudoun County Virginia's "Data Center Alley."  Virginia keeps approving new data centers and local utilities do not have enough electricity available to power them.  PJM designed a new long-distance extension cord that plugs the data centers into new sources of power beginning at the 502 Junction substation in southwestern Pennsylvania.  

Of course, substations do not generate electricity.  They serve as traffic circles to direct energy in different directions via high-voltage transmission lines.  PJM's new transmission snarl, err I meant to say MARL (MidAtlantic Resiliency Link), begins at 502 Junction substation and ends at the new Aspen substation in Data Center Alley.  But what generation sources are connected to 502 Junction that can be directed to Data Center Alley?  I'll give you two guesses...
Fort Martin and Harrison
That's right... the two generators at which FirstEnergy can no longer reduce emissions are directly connected to 502 Junction.
Picture
The red lines on the map are existing 500kV transmission lines that connect Harrison and Ft. Martin directly to 502 Junction.  The new MARL project will take it from there, right to data centers in Loudoun County.

This is the reason FirstEnergy has abandoned its 2030 interim greenhouse gas goal.  In late 2023, PJM approved MARL.  PJM approved the project due to 7500 MW of new data center load and the retirement of 11,000 MW of fossil fuel generation in its eastern region.  Resource adequacy and state energy policy initiatives at work.

So, what does this mean?  It means that instead of reducing the greenhouse gas spewed into the West Virginia air from FirstEnergy's Ft. Martin and Harrison power stations, FirstEnergy is going to be increasing their carbon emissions.  All for benefit of No. Va.'s data centers and the selfish and destructive state energy policies of Virginia and its neighbors.

Northern Virginians who keep approving data centers despite knowing there is no way to power them without imports from West Virginia are directly responsible *COMPLICIT* in increased air pollution, health and environmental impacts caused by continued mining and burning of coal in West Virginia.

Why is this okay?

Don't turn away from this.  OWN IT.  Don't blame your elected officials or throw up your hands in despair.  Make your elected officials OWN IT.  Make them publicly say that it's okay to increase carbon emissions to power the data centers they approve.  Of course they won't.  FirstEnergy has just handed you a sledgehammer to stop data center sprawl.  Use it.

Every time you turn on a light switch in Northern Virginia, you are increasing carbon emissions.  That's right... the coal-fired power from West Virginia won't just power the data centers... it will power all of Northern Virginia.  Give your climate guilt a great big hug, it's going to be your constant companion for years.

PJM's new transmission plans to power data centers in Northern Virginia are going to increase carbon emissions.  End of story.
0 Comments

What Will Be On New PJM Lines?

8/25/2023

0 Comments

 
PJM Interconnection is the grid planner for the Mid-Atlantic region.  PJM's job is to keep the grid reliable and the electricity markets competitive.  When load increases in PJM's region without a corresponding increase in generation of electricity, reliability suffers.  When reliability is threatened, PJM springs into action and plans new transmission to solve the impending crisis.  If PJM did not act, we'd soon experience brown outs and black outs and the whole PJM system would crash.  The most logical solution for PJM would be to order new generation near sources of increased load.  However, PJM cannot order new generation, it can only order new transmission.  Electric generation is a market-based, competitive endeavor.  If demand increases prices in a certain load pocket, then the generation market receives a signal that it would be profitable for new generation to build for that load.  It works, in theory, but sadly not in practice.  PJM's  reliability focused transmission planners never let the market work to spur new generation.  When prices increase, or reliability issues crop up on the horizon, PJM orders new transmission to solve the problem before any new generators are even contemplated.  PJM complains about the loss of baseload generation without replacement, but fails to acknowledge its own role in creating the problem.

Over the past decade or so, Northern Virginia has become the data center capital of the country.  Data centers use a LOT of electricity.  This recent article says that Amazon data centers in Northern Virginia use half as much electricity as New York City every day, and 35% more than the entire power grid of the company's hometown city of Seattle.  That's a huge electric load currently being built out in Northern Virginia without a corresponding increase in electric generation.  PJM says the data centers are creating a reliability issue and it has opened a request for proposals to solve it using transmission.  The goal is to export a whole bunch of electricity to Northern Virginia, and PJM's utility members wasted no time in creating new transmission lines that would connect the generators they own to Northern Virginia.
Picture
One such proposal from FirstEnergy envisions two new 500kV lines from West Virginia to a substation in Frederick County, Maryland.  Other utilities have proposed new lines from that substation to Northern Virginia, completing the new extension cords.

Extension cords are exactly what these new transmission lines are.  They plug in at struggling FirstEnergy-owned electric generators in West Virginia and provide a pathway for additional electricity generated in West Virginia to power the data centers in Northern Virginia.

The map shows the northern line of this proposal beginning at Fort Martin, West Virginia.  Fort Martin is the location of FirstEnergy's coal-fired Ft. Martin Power Station.
Picture
The plant uses more than 2.8 million tons of coal annually and at full capacity the plant’s generating units can produce more than 26 million kilowatt-hours of electricity daily.  Read more here. 

Of course, nobody wants coal-fired electricity any more and FirstEnergy has been toying with closing or selling some of these plants.  And then the PJM serendipity fairy arrived!  PJM needs transmission to bring a new supply of power to No. Va., and FirstEnergy can bolster the future economic success of its failing generators by connecting it to data center load.  And FirstEnergy's proposal was born.

The southern line of FirstEnergy's proposal is shown on the map as beginning at Pruntytown, WV.  Pruntytown is a gigantic substation where many electric generators in the area connect to the grid.  One such plant is FirstEnergy's Harrison Power Station in Haywood, West Virginia.

Picture
Harrison uses more than five million tons of coal annually and at full capacity the plant’s generating units can produce over 47 million kilowatt-hours of electricity daily.  Read more about Harrison here.  FirstEnergy's bottom line wins again with this proposal!

But did anyone ask Northern Virginia if they wanted to import dirty coal-fired electricity from West Virginia to power their data centers?  PJM?  FirstEnergy?  Dominion?  These entities are going to have a really hard time selling this to a community with clean energy goals and aspirations.  The D.C. metro area is so worried about climate change that they have closed many fossil fuel generators in their own neighborhoods.  Why would these people just look the other way and shrug about increasing their carbon footprint every time they turn on the light switch?  Would local governments in Northern Virginia keep approving new data centers that need power if they knew they were increasing regional air pollution?  Where's the tipping point here?

In addition to the burning of more coal to produce more electricity in West Virginia, FirstEnergy's proposals also plan on hundreds of miles of new transmission rights of way across private property between West Virginia and Northern Virginia.  None of these affected landowners need this new electric supply.  It's simply passing through on its way to corporate users in D.C.'s growing urban sprawl.

Of course, FirstEnergy's proposal is only one of 72 that PJM received.  Other utilities have proposed connecting their nuclear and gas fired power stations in south eastern Pennsylvania to the data center load via new transmission lines.  Numerous proposals begin at the Peach Bottom Atomic Power Station in Delta, PA and the gas-fired York Energy Center in the same town.  Still other proposals want to connect the data center load to American Electric Power's massive 765kV transmission system in the Ohio Valley, where numerous fossil fuel plants are struggling to survive.  See the 765 lines on this map:

Picture
The endpoint of AEP's 765kV system in Virginia is at a substation called Joshua Falls.  New lines beginning at Joshua Falls connect to the data center load as shown on this proposal map submitted to PJM by AEP subsidiary Transource.
Picture
Northern Virginia communities need to go into this new power supply for their data centers with their eyes wide open.  Are all the "benefits" they are receiving from the massive data center build out worth increasing their carbon footprint?  Why are other communities in rural areas hundreds of miles from the data centers being forced to sacrifice their land and in some instances, the very air they breathe, so that Northern Virginia counties can increase their tax revenue and their sprawl?  If these counties are receiving all the benefits from the data center buildout, shouldn't they also step up and shoulder the negative impacts by building new coal, gas, and nuclear power stations in their own communities?

There has to be a better solution than this!
0 Comments

Transmission Leftovers

7/16/2023

2 Comments

 
Some things are better the second time around, like lasagna and chili.  Transmission projects, however, are not good leftovers.  Once a transmission idea is proposed to the public, vehemently contested, and eventually shelved as unneeded and impossible, it can never come back from the dead.

Or can it?

The Infrastructure Investment and Jobs Act and the Inflation Reduction Act have created a new transmission feeding frenzy from coast to coast.  Now that the government is giving away your tax dollars to provide incentive to build new transmission "for renewables," utilities and transmission developers are falling all over themselves to belly up to the buffet.  There is no actual plan for what transmission needs to be built, any transmission will do.  It's about quantity, not quality.  They just can't propose transmission fast enough.  And apparently some utilities are simply recycling old transmission projects from the last decade that were never built.

Remember the Mid-Atlantic Power Pathway, or MAPP, project?  Proposed around 2007, this hotly opposed transmission project across Maryland's eastern shore was finally abandoned several years later, citing lack of need.  The utilities behind this horrible idea were fully reimbursed for their sunk costs by ratepayers who would have "benefited" from the project.  If my memory serves, it was something like $80M that we paid for a transmission project that was never constructed.

The MAPP project is back, one of dozens of new transmission proposals currently being evaluated by grid planner PJM.  They even recycled the name... once again calling it MAPP.
Project title:  Mid-Atlantic Power Pathway (MAPP)

Project description:  Exelon is proposing a 230 mile, 500 kV AC / 400 kV DC high-voltage transmission line originating in Northern Virginia, crossing Maryland, traveling up the Delmarva Peninsula and terminating in southern New Jersey.

Do they think the folks who fought MAPP have forgotten?  It's only been 15 years.  They remember, and many are still around, with all the knowledge they gained fighting MAPP the first time.

Transmission fatigue is a thing.  Communities who have fought a transmission line are instantly opposed to another proposed for the same area, and they know what to do because they've ridden in this rodeo before.  A recent transmission proposal through New Hampshire is giving communities that fought the scrapped Northern Pass project PTSD.
When four representatives of National Grid came before Concord City Council on Monday to start the long process of expanding a power line through the state bringing electricity from HydroQuebec, they soon encountered a ghost.

“Our community still suffers from PTSD with regard to Northern Pass,” Councilor Jennifer Kretovic told them. “When you mention the words HydroQuebec, that will automatically raise concern.”

The four representatives nodded glumly.
And stupidly, I might add.  Transmission is bad enough without ghost projects adding to the hatred.

It seems that every contested and vanquished transmission project from the past 15-20 years has been resurrected.

Remember PATH, the Potomac-Appalachian Transmission Highline?  It's back.  But instead of just the revised, re-routed project that PATH finally settled on, former PATH partner FirstEnergy has proposed BOTH the original PATH route through Morgan, Berkeley and Jefferson Counties AND the revised PATH route through Frederick County, VA, southern Jefferson County, WV, Loudoun County, VA and Frederick County Maryland.  This is FirstEnergy's recent proposal for PJM's competitive transmission window.  On a map, it looks like this:
Picture
The northern line on the map is described like this:
Component title:  Fort Martin - Doubs 500 kV #1 Line

Project description: 
Construct ~158 miles of new 500 kV line from Fort Martin Substation to Doubs Substation.Terminate the new transmission line and revise relay settings at Doubs and Fort Martin substations.Install fiber OPGW along the new line route. The construction of this new line will require the acquisition of 158 miles of new right-of-way, forestry clearing, permitting, and access road construction. Re-terminate the Bismark 500 kV Line at Doubs Substation. Aerial LiDAR will be required. This new transmission line will require Proposal Components 1 (Doubs Substation - Install500 kV Breaker), 2 (Doubs Substation - Expand 500 kV), and 4 (Fort Martin Substation - Install 500kV Breaker) to be completed.

This new 500 kV line will be constructed in West Virginia, Virginia, and Maryland. Full Applications
will be required in each state. - It is assumed that the new 500 kV line will parallel existing ROW for approximately (85.6) miles and require (74.4) miles of new ROW not adjacent to existing ROW. It is assumed that no existing lines will be overbuilt with double circuit structures, but existing line rebuilds will be considered where applicable. - Approximately (695) parcels will be affected by the line route. Assumed 5% condemnation (35 parcels).

The right-of-way width is assumed to be 200 ft. This width is based on the widest ROW needed for
500 kV and does not account for structure configuration or span lengths. Widths needed may vary upon final design.

The new Fort Martin-Doubs #1 500 kV Line will be constructed on double circuit 500 kV tubular
steel monopole and two-Pole structures. The second 500 kV circuit is to be left vacant and installed at a future date. - The average span length is 1200 ft. - It is assumed that the new double circuit monopole structures will have an average height of 180 ft. Final structure heights will need to be determined during project development. FAA filing and application may be required. - The new structures will utilize custom 500 kV V-string and double I-string suspension and dead-end insulator assemblies.

This new 500 kV line provides a direct connection from the west side of the system to the east
side. - This new line provides the ability to install a second Fort Martin - Doubs 500 kV Line on the same structures, without additional right-of-way acquisition. - This new line route will provide the opportunity to loop the Fort Martin - Doubs 500 kV Line into Bedington and/or Black Oak substations in the future, if necessary for reliability or resiliency. - Greenfield construction is assumed due to outage constraints, but existing rights-of-way and corridors to rebuild lower voltage lines will be considered where applicable.
A portion of the southern line on the map from Meadow Brook to Doubs is described like this:
Component title:  Meadow Brook - Doubs 500 kV Line

Project description:  Construct 55.3 miles of new 500 kV line from Meadow Brook Substation to Doubs Substation.Terminate the new transmission line and revise relay settings at Doubs and Meadow Brook substations. Install fiber along the new line route. The construction of this new line will require the acquisition of 55.3 miles of new right-of-way, forestry clearing, permitting, and access road construction. Re-terminate the Meadow Brook - Loudon & Meadow Brook - Front Royal 500 kV lines at Meadow Brook Substation. Aerial LiDAR will be required. This new transmission line wil lrequire Proposal Components 1 (Doubs Substation - Install 500 kV Breaker), Component 2 (Doubs Substation - Expand 500 kV), and Component 3 (Meadow Brook Substation - Expand 500 kV) to be completed.

This new 500 kV line will be constructed in Virginia, West Virginia, and Maryland. Full Applications
will be required in each state. - It is assumed that the new line will parallel existing ROW for approximately (22.8) miles and require (32.5) miles of new ROW not adjacent to existing ROW. It is assumed that no existing lines will be overbuilt with double circuit structures, but existing line rebuilds will be considered where applicable. - Approximately (146) parcels will be affected by thel ine route. Assumed 5% condemnation (7 parcels).

The right-of-way width is assumed to be 200 ft. This width is based on the widest ROW needed for 500 kV and does not account for structure configuration or span lengths. Widths needed can vary upon final design.

This new line will be constructed on single circuit 500 kV tubular steel monopole structures with an
average span length of 1200 ft. - The new structures will utilize custom 500 kV V-string and double I-string suspension and dead-end insulator assemblies. - New single circuit structures will have an average height of 150 ft.

This new 500 kV Line will provide an additional and much shorter electrical path between Meadow
Brook and Doubs linking the Black Oak-Bedington corridor with the 'AP South' corridor. - Greenfield construction is assumed due to outage constraints, but existing rights-of-way and corridors to rebuild lower voltage lines will be considered where applicable.
In addition, FirstEnergy proposed building a new 50 mile greenfield transmission line from Pruntytown to Meadow Brook.

It's not an "either/or" proposition.  FirstEnergy wants to build BOTH old PATH ideas this time.

Here we go again!

Is this new transmission required to expand renewable power?  Look at the map, it's self-explanatory.  PJM is soliciting proposals to move more coal-fired electric generation from plants at Ft. Martin and Pruntytown into the Washington, D.C. suburbs.  New generation is needed there because these areas have closed a whole bunch of the "dirty" coal and gas fired generation that used to keep their lights on.  Instead of replacing what they closed with local renewables, they're burying their heads in the sand and pretending they don't need any new generation.  However, they're also building new data centers that use an enormous amount of power and leaving it up to grid planner PJM to find a way to keep the lights on and the data centers humming.  The new PATH is one proposal for PJM to do just that.  Hardly "clean and green" is it?  It's a step back 20 years in time, when PATH was proposed to move 5,000 MW of coal-fired electricity from southern West Virginia to the D.C. metro area.

So, what happens next?  PJM says it will select projects from its huge proposal list in September.  Once selected, it proposes to have the favored projects approved by its Board in December of this year.  See timeline here (these projects are in 2022 RTEP Window 3):
Picture
After being beaten into submission the first time, PATH abandoned its project and collected over $150M from electric customers like us for a project that was never built.  How much will it cost us the second time around? 

Keep your eyes on this one.  PATH did not happen the first time due to widespread opposition.  We're still here and we remember.
2 Comments

FirstEnergy Gets Slap On Wrist For Bilking Ratepayers

2/9/2022

0 Comments

 
Picture
Well, that will teach them!

FERC recently released the results of its audit of FirstEnergy transmission company rates.  The audit found that some of FirstEnergy's lobbying costs had been passed through in consumer electric rates.  The audit also found that FirstEnergy had made other accounting "mistakes" that improperly increased the rates the company collected.  The exposure of FirstEnergy's accounting "mistakes" could result in the refund of millions.

Why is it that all utility accounting "mistakes" are in the company's favor?  I've never seen a regulatory audit where it was determined that an accounting mistake was in the customer's favor.  Maybe they're not mistakes at all... maybe they are "on purposes"?

FERC's audit report even states that perhaps these "mistakes" were not innocent.
The DOJ complaint and audit staff’s discussions on internal controls during onsite interviews of FESC employees raised audit staff’s concerns about the existence of significant shortcomings in FirstEnergy and its subsidiary companies’ controls over financial reporting, including controls over accounting for the costs of civic, political, and related activities, such as lobbying activities, performed by and on behalf of FirstEnergy and its subsidiaries. Moreover, these controls may have been circumvented in ways designed to conceal the nature and purpose of expenditures made and, as a result, that led to the improper inclusion of lobbying and other nonutility costs in wholesale rate determinations.
They did it on purpose to steal from consumers.

But, wait, there's more!
Even more concerning, several factual assertions agreed to by FirstEnergy in DPA and the remedies FirstEnergy agreed to undertake, point towards internal controls having been possibly obfuscated or circumvented to conceal or mislead as to the actual amounts, nature, and purpose of the lobbying expenditures made, and as a result, the improper inclusion of lobbying and other nonutility costs in wholesale transmission billing rates.
Yes, they did it on purpose.  It was no accident.

So, what happens to a utility when FERC finds that it willfully practiced creative accounting in order to collect more from its customers than it was entitled to?

Slap on the wrist.  It must revise its policies, train its employees, conduct a labor study, and submit a report of how much it will refund to customers.  All these activities will be paid for by the ratepayers who were harmed.

FirstEnergy is not fined or penalized in any way.  As long as it spits out a bunch of paper and empty promises, it can continue on bilking ratepayers.

This is what always happens when FERC's Division of Audits performs a review and finds the same old errors committed by almost all utilities that serve to unlawfully increase electric rates.  The utilities simply made a "mistake" and new policies and training will fix it and prevent it from happening again.

But it always happens again.

When is FERC going to punish its utility pets?

Compare to the way FERC goes after electricity market traders who commit similar "mistakes" that may result in excess profit.  FERC hounds them to the ends of the earth and demands ridiculous monetary penalties.  But if you're a utility, you're allowed to steal from ratepayers with only a slap on the wrist.

FERC's random audits don't do a thing to deter utility accounting fraud.  When utilities are allowed to keep making the same "mistakes" over and over, it's a criminal enterprise that deserves penalties.  Utilities have stolen billions from consumers by committing accounting fraud... and they continue to get away with it.

Disappointing... and infuriating.
0 Comments

Might I Suggest Schadenfreude Stadium?

1/5/2021

0 Comments

 
Try though I did to resist gawking at the train wreck that is FirstEnergy these days simply because it's a giant distraction, I simply couldn't resist the belly laugh I got from this article that suggested renaming the Cleveland stadium "Company A Stadium."
That's right... Cleveland gets to be embarrassed for another 10 years by having its football stadium named for a company mired in dirty deals.  Renaming the stadium gives me the giggles (and endless opportunities).  However, instead of focusing on the company, and creative names for it (WorstEnergy, Perpetual Estimate, or the ever popular FirstInfluence) might I suggest we focus on its victims?  Because that's who's thoroughly enjoying the schadenfreude oozing out of this spectacle... Schadenfreude Stadium.  It even has that kicky alliterative punch.  And who doesn't enjoy watching the Browns get their butt kicked on their home turf?  If only football could be influenced by corporate cash, lobbyists and front groups...

The schadenfreude is already thick at the stadium.  The "deal" to put FirstEnergy's name on the stadium was mired in muck from the very beginning.  Fired FirstEnergy CEO Chuck Jones (at the time merely a CEO in waiting) demonstrated for everyone who would listen that FirstEnergy's influence was vast... and he seemed rather proud of it.  Was this the beginning of the end for FirstEnergy?  While FirstEnergy's Empire of Influence had been going strong for decades, previous CEOs like "Tony the Trickster" Alexander didn't parade that stuff out in public like Chatty Chuck.  Chatty Chuck seemed to prefer the transparency of everyone knowing just how powerful he was.  Was it arrogance?  Or mere stupidity?  We may never know, but one thing's for sure.... First Energy's influencing days seem to be over for now.  Or else they're just going to have to get a little more cloak and dagger in carrying it out.

There are several audits of the company and its affiliates going on in two different states, in addition to the federal investigation that was made public last year.  Ohio regulators are looking into FirstEnergy's political and charitable expenditures.  The New Jersey BPU recently decided to open an audit of FirstEnergy's subsidiary in that state after its credit was downgraded.

Pardon the sickening simile, but FirstEnergy is like a giant boil that just got lanced... and all kinds of unspeakable things are leaking out of it.  One might be surprised if they didn't know better.  But for those who have been victims of FirstEnergy's Empire of Influence, its a schadenfreude shindig!

A new report claims that FirstEnergy funded a front group that attacked Cleveland Public Power last year.  The group, Consumers Against Deceptive Fees, claimed to be an "advocate" for CPP customers, although it was funded by FirstEnergy.  What reason would FirstEnergy have to spend money "advocating" for the customers of another utility?  Competitive ones, perhaps, but not "advocacy" ones.  Just another expensive front group funded by FirstEnergy, pretending to be an organic "grassroots" uprising of the people, although it is unlikely any unaffiliated "consumers" were involved.

FirstEnergy should stop with the front groups.  They rarely succeed... and they're quite expensive.  Who's paying for all this?  That's what the Ohio Consumers Council wanted to know in the Ohio case... did any of FirstEnergy's influencing costs end up in consumer electric bills?  Of course, FirstEnergy objected to answering.

How long can FirstEnergy continue to pretend the company had no idea how much influence was being purchased to support its money-making schemes?  And when will state regulators in the other states FirstEnergy serves launch their own canoes into FirstEnergy's river of filth?  Sounds like it may soon be time for a hostile takeover of certain FirstEnergy fiefdoms, either piecemeal, or swallowed whole by one of its fiercest competitors who may want to increase its own utility empire.

If Cleveland renames its football stadium Schadenfreude Stadium, I might even be tempted to visit.  Not to watch a game, however, but to soak up the schadenfreude.  I probably won't be alone.

0 Comments

Someone Finally Spits In Chatty Chuck's Mashed Potatoes

10/31/2020

2 Comments

 
Back at the end of 2014, Chatty Chuck Jones was poised to take over as CEO of FirstEnergy.  At that time, I wrote:
FirstEnergy's soon to be president and CEO is Chatty Chuck Jones, the famous deal-maker who is completely out of touch with the real world the rest of us inhabit.  Someday, someone's going to spit in his mashed potatoes.
And on Thursday night, the FirstEnergy Board hawked up a big one.
Picture
Picture
FirstEnergy fired Jones and two others in the wake of the bribery scandal involving Ohio Speaker of the House Larry Householder, and on the same day two others plead guilty, including a FirstEnergy lobbyist.

A couple months ago, Chatty Chuck denied FirstEnergy had done anything wrong in the scandal, however I think some indictment documents said that the FirstEnergy CEO was chauffeured to the scene of some evil deed or other so that he could see it for himself.  I guess that was sort of like sitting in the outdoor seats at a Browns game even though you had a perfectly good VIP Suite from which to watch the game.  Oooh!  A daring risk-taker!

If FirstEnergy did nothing wrong, how is it that Chatty Chuck and friends did something wrong?
The company said the three executives were fired after an internal review committee determined they “violated certain FirstEnergy policies and its code of conduct.” The company didn’t offer additional details in its press release, and a company spokeswoman declined to elaborate.
Looks like Chatty Chuck gets to eat the spitty mashed potatoes on FirstEnergy's plate. 

Don't cry for Chatty Chuck though... he's made a bundle.
Documents filed earlier this month involving a shareholder’s lawsuit in U.S. District Court in Akron show that Jones and other top executives at FirstEnergy sold off millions of dollars of company stock from March 1, 2017, to March 1, 2020.
The records allege that Jones “sold or otherwise disposed of over 788,000 shares” of FirstEnergy stock for $31 million during that time.
Who else got sacrificed to save FirstEnergy's bacon? 
Senior Vice President of Product Development, Marketing, and Branding Dennis Chack, and Senior Vice President of External Affairs Mike Dowling
Never heard of Chack, but Dowling sounds familiar.  Hmm.... where have I seen that name before?  I know!  It was woven through FirstEnergy's 270,000+ page data dump in the PATH case.  I am so not surprised.

All utilities thrive on corruption in one form or the other.  It's all about regulatory capture.  Although regulation is part of the bargain utilities strike in order to maintain their monopolies, there's also a driving need to make money.  These two things cannot co-exist.

So, what's next for Chatty Chuck?  Maybe he can wait tables and collect some cash for keeping his mouth shut about diner conversations.  Or maybe he can sweep up at FirstEnergy stadium to keep busy?  Or maybe he'll just retire.  I'm kind of wondering how close the trio of terror were to retirement anyhow?  Not a spring chicken among them.

And can we sing this old favorite once again?
2 Comments

Ut-oh, Utility Rainmakers.  UTT-OHHHH!

7/22/2020

2 Comments

 
Investor-owned utilities are all about the Benjamins.  They're only interested in providing a public service because it's profitable.  There is no honor among thieves.

In the past couple weeks, federal investigators have dropped the hammer on two of the biggest... two of the biggest criminal enterprises in the utility business.  Are more coming?  I'd say it's likely at this point.  Be afraid, utility rainmakers, be very afraid!
Last week, Exelon subsidiary ComEd agreed to pay a $200M fine for its part in a years-long bribery scheme involving the Speaker of the Illinois House, and possibly the Illinois Commerce Commission.  According to court documents, ComEd arranged no-work "jobs", contracts, and appointments to both the ICC and its own corporate Board of Directors in exchange for political favors from House Speaker Michael Madigan.

Here's a summary from the document:
COMMONWEALTH EDISON COMPANY,
defendant herein, corruptly gave, offered, and agreed to give things of value, namely, jobs, vendor subcontracts, and monetary payments associated with those jobs and subcontracts, for the benefit of Public Official A and Public
Official A's associates, with intent to influence and reward Public Official A, as an agent of the State of Illinois, a State government that during each of the twelve-month calendar years from 2011 to 2019, received federal benefits in excess of $10,000, in connection with any business, transaction, and series of transactions of $5,000 or more of the State of Illinois, namely, legislation affecting ComEd and its business;
In violation of Title 18, United States Code, Section 666(a)(2).
I was particularly touched by this scheme.
Hiring of Public Official A's Associates as Vendor "Subcontractors" Who Performed Little or No Work for ComEd

ComEd employees and agents, including third-party consultants and lobbyists were subject to Exelon's Code of Conduct. Exelon's Code of Conduct, applicable beginning in 2015, required employees and agents to: (a) "(k]eep accurate and complete records so all payments are honestly detailed and company funds are not used for unlawful purposes"; (b) "[c]onduct due diligence on all potential agents, consultants or other business partners"; and (c) "[n]ever use a third party to make payments or offers that could be improper." Exelon's Code of Conduct also prohibited bribery and listed as an example of a prohibited bribe: "Providing something of value for the benefit of a public official in a position to make a decision that could benefit the company." Beginning no later than in or around 2011, Public Official A and Individual A
sought to obtain from ComEd jobs, vendor subcontracts, and monetary payments associated with those jobs and subcontracts for various associates of Public Official A, such as precinct captains who operated within Public Official A's legislative district. In or around 2011, Individual A and Lobbyist 1 developed a plan to direct money to two of Public Official A's associates ("Associate 1" and'' Associate 2") by having ComEd pay them indirectly as subcontractors to Consultant 1. Payments to Associate 1 and Associate 2, as well as later payments to other subcontracted associates of Public Official A. continued until in or around 2019, even though those associates did little to no work during that period.
Consultant 1 agreed in 2011 that Public Official A's associates would be identified as subcontractors under Consultant 1's contract and that ComEd's payments to Consultant 1 would be increased to cover payments to those subcontractors. Between in or around 2011 and 2019, Consultant 1 executed written contracts and submitted invoices to ComEd that made it falsely appear that the payments made to Company 1 were all in return for Consultant 1's advice on "legislative issues" and "legislative risk management activities," and other similar matters, when in fact a portion of the compensation paid to Company 1 was intended for ultimate payment to Public Official A's associates, who in fact did little to no work for ComEd. Consultant 1 and Company 1 did little, if anything, to direct or supervise the activities of Public Official A's associates, even though they were subcontracted under and received payments through Company 1. Moreover, because they were paid indirectly through Company 1, the payments to Public Official A's associates over the course of approximately eight years were not reflected in the vendor payment system used by ComEd, and as a result, despite that Public Official A's associates were subcontracted under and receiving payments through Company 1, no such payments were identifiable in ComEd's vendor payment system.
So, because ComEd wanted to make gravy payments to certain individuals it hid them as "subcontractors" within a legitimate contractor's contract.  Why, it's almost like that time when PATH hired former Joe Manchin Chief of Staff Larry Puccio and decided that he would be paid through the company's contract with Charles Ryan Associates, although Larry wouldn't give speaking events like the other subcontractors.  Even PATH's accountants got suspicious, however, when Larry's bills showed up in Charles Ryan's monthly detail without any statement of work performed.  All of this made the FERC Administrative Law Judge question whether Larry had actually done any work at all...

I wonder if ComEd and PATH were comparing notes on hiding the gravy $$$?

And yesterday, the federal boogeyman showed up in Ohio to clean house in an alleged $60M bribery scheme involving a FirstEnergy subsidiary and Ohio's Speaker of the House Larry Householder.  You can read those court documents here.

In this instance, the schemers were arrested and charged with conspiracy to participate in an enterprise's affairs through a pattern of racketeering activity.  RICO.  UT-OHHH FirstEnergy!  Quick, NEO's to the basement bunker to use their bodies as human shields to to protect Chatty Chuck!

Bribery, extortion and efforts to defraud the government, FirstEnergy?  Who woulda thunk it...

Oh, wait... I've read a whole bunch of their internal documents over the years.  I guess I woulda thunk it.  Schadenfreude!
Whew!  That was fun, wasn't it?

I'm going to bet that all investor-owned utilities buy elected officials and regulators, either with cash, contracts, fake "jobs", maybe even hookers and blow, who knows?  Looks like the utility will supply whatever it takes to make sure your elected official or regulator is working for the them, and not you.  But our government has been watching... and now heads are rolling.  It's about damned time.

UT-OH utility rainmakers.... who's going to be next?
2 Comments
<<Previous

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.